Single Blog Title

This is a single blog caption

U.S. Construction Firm Lauds Versatility of Modulift Beams

Modulift spreader beams combined with other rigging equipment in 19 different configurations to complete over 200 lifts during modular construction of the citizenM Hotel in South Lake Union, Seattle, Washington recently.

citizenM employed a construction method that involved piecing together modular parts that were manufactured by Modulift’s customer, Polcom, of Poland. The seven-storey building includes six floors of modular units, each one requiring 19 unique lifts—the beam and sling lengths were different each time—and 228 in total throughout the project.

Construction firm Mortenson, which has built over 100 hotels across North America, accepted a scope of work as general contractor to assemble the 264 key modular building, which would eventually boast meeting rooms, a living room, bar area, and gym, in addition to the luxury bedrooms that represented the majority of the lifts by tower crane.

Jack McCaskill, project engineer, from the Seattle Operating Group at Mortenson, explained that diversity of rigging was required as the modules varied in size; the largest measured 10 ft. wide by 51 ft. long and weighed 45,000 lbs. (approx. 20.5t). Some modules had six lifting points and others had eight. Further, not all of those points were in line and some modules had offset centres of gravity. The heights of lift also increased as the hotel took shape, with the final storey reaching 70 ft. from street level.

Spreader beams were used in 19 different configurations in 200+ lifts. Photo: Mortenson

Modulift prescribed cascading rigs, consisting of spreader beams, slings, and shackles, which proved the most cost-effective below-the-hook solution. For the eight-point lifts, a one-over-two-over-four configuration was used, consisting of seven spreader beams at different levels; and for the six-point lifts, a one-over-one-over-three rig comprised of five spreaders at different levels.

Flexible solution

Sue Spencer, technical director at Modulift, said: “Whenever Polcom begins a new product, they ship the equipment to site and we provide the rig drawings as their technical partner. This type of rig is flexible and nicely balanced. We could have come up with a custom designed frame, but this would have been heavier and more costly—and it would have been rigid rather than flexible. Also, because the customer has used our equipment on many module installations, they had the spreader beams required in their fleet. They only had to purchase a small quantity of spreader beam struts.”

Due to site constraints encountered once the project was underway, Modulift was called upon to make modifications to five of the rigging arrangements. Spencer explained that alterations were necessary because of obstructions caused by scaffolding. She added: “We had to redesign the rigs so they were much lower in height; we achieved it by reducing the sling angles above each spreader beam and in some cases at less than a 45-degree angle beneath. We also changed the types of connection slings to the spreaders to avoid any clashing between the slings and the beams due to lower [sling] angles.”

Modulift provided cascading rigs, consisting of spreader beams, slings, and shackles, which proved the most cost-effective below-the-hook solution. Photo: Mortenson

MOD 24, MOD 34, MOD 50, and MOD 70 spreader beams were all utilised during the project. The longest and largest was a 30-ft.-long MOD 70, while the smallest and shortest was a MOD 24 at 5 ft. The slings were predominantly chain slings with shorteners so that the lengths could be adjusted to accommodate the aforementioned offset centres of gravity, with polyester slings to connect to the beams for the lower height rigs.

McCaskill pointed out that the writing, visible on the side of the modules, identified the units by room number within the hotel. It was also used to communicate the sequence at which the modules needed to be set into place. He concluded: “Modulift has been outstanding, both in their efforts to help our project and in the quality of their work.”

MOD 24, MOD 34, MOD 50, and MOD 70 spreader beams were all utilised. Photo: Mortenson

Leave a Reply

Please send news and information on new products to: [email protected]